New Delhi, July 31 (PTI) The Indian Railways is going full steam to achieve the target of covering the 245-km long Delhi-Chandigarh distance in flat two hours despite many curves on the proposed semi-high speed route.
The Delhi-Chandigarh corridor, one of the busiest routes in north India, is slated to be first semi-high speed project being taken up by the state-owned transporter to run trains at maximum speeds of 200 kmph with French help.
There are about 10 major curves spanning over 32 km on the existing Delhi-Chandigarh rail route.
The public transporter will not go for land acquisition required for straightening up several curves on the Delhi- Chandigarh semi-high speed corridor and instead opt for slowing down while negotiating the track, according to the railways.